NEWS  
 
11.06.2008
BrightSource Energy / Luz II Dedicate Solar Energy Development Center


21.05.2008
Arnold J. Goldman addresses the Renewable Energy and Beyond conference at Tel Aviv University.


13.05.2008
BrightSource Energy Exceeds $115 Million in Latest Round of Funding


13.05.2008
Luz II is invited to participate in the Israeli Presidential Conference 2008: “Facing Tomorrow”


20.03.2008
Boiler Installation on Top of the Tower.
On Thursday 20th March 2008, the Boiler was successfully lifted on top of the tower by the largest crane of the country. This significant event is the result of months of planning and construction effort.

05.03.2008
Arnold J Goldman address the Washington International Renewable Energy Conference (WIREC)


13.03.2008
Boiler leaving Manufacturer in Italy and reaching the site six delays later on the 19th March.


12.03.2008
Tower Levels 7, 8, 9, 10 lifted and installed successfully.


11.03.2008
Largest crane of the country assembled.
The largest crane of the country is to be used for lifting the Boiler of top of the tower. Four days are required to complete crane assembly on site.

02.03.2008
Condensate Vessel delivered to site.
The 25 Ton Condensate Vessel has been delivered today to the site

24.02.2008
Air Cooled Condensers delivered and installed at the Tower.


11.02.2008
Tower Levels 3,4,5,6 lifted and installed successfully.
On Monday 11th February 2008, LUZ II achieved another major
milestone in the Pilot Plant construction with the lifting and
installation in final location of Tower levels 3,4,5,6 out of a total of
10 levels.


<<  < | 1 | 2 | >  >>     Total Pages: 2
 
  back to top  
Search:    
  About Us | Technology | Projects | Team | News | Press | Contact Us | Site Map

Copyright©1999-2007 LUZ II- All rights reserved. Created By WolfMedia